§ 15.28.020. Amendments to the International Plumbing Code.


Latest version.
  • The following sections of the International Plumbing Code are amended to read as follows:

      101.1 — Title: These regulations shall be known as the International Plumbing Code of the City of Clovis hereinafter referred to as "this code".

      106.6.2 — Fee Schedule: The fees for all plumbing work shall be as indicated in the following schedule:

    Plumbing

    Each Plumbing Fixture/waste discharging device $ 3.00 per item
    Water distribution system $ 3.00 per item
    Each house sewer $ 3.00 per item
    Each septic tank $ 4.50 per item
    Each grease trap $ 4.50 per item
    Water Heater — electric $ 3.00 per item
    Each swimming pool $37.50 per item
    Each water conditioner $ 4.50 per item
    Each yard sprinkler system $10.00 per item
    Each vacuum breaker/backflow device $ 3.00 per item
    Each hot water solar system $15.00 per item

     

    Gas

    Each yard line $ 4.50 per item
    Each capped opening $ 3.00 per item
    Each water heater $ 3.00 per item
    Each wall heater $ 3.00 per item
    Each circulating heater $ 3.00 per item
    Each range $ 3.00 per item
    Each floor furnace $ 5.00 per item
    Each dryer $ 3.00 per item
    Each mercury test $ 7.50 per item

     

    Miscellaneous

    Administrative Fee (per permit) $15.00
    Re-inspection of any failed work $20.00
    Red Tag — per address $ 3.00
    Final Inspection (new construction) $ 7.50
    Inspection after normal business hrs. $30.00

     

     106.6.3 Fee Refunds — specify percentage:

      (2) Not more than fifty percent (50%) of the permit fee paid when no work has been done under a permit issued in accordance with this code.

      (3) Not more than fifty percent (50%) of the plan review fee paid when an application for a permit for which a plan review fee has been paid is withdrawn or canceled before any plan review effort has been expended.

      108.4 — Violation penalties: Any person who shall violate a provision of this code or shall fail to comply with any of the requirements thereof or who shall erect, install, alter or repair plumbing work in violation of the approved construction documents or directive of the code official, or of a permit or certificate issued under the provisions of this code, shall be guilty of a misdemeanor, punishable by a fine of not more than five hundred dollars ($500.00) or by imprisonment not exceeding ten (10) days, or both such fine and imprisonment. Each day that a violation continues after due notice has been served shall be deemed a separate offense.

      108.5 — Stop Work Orders: Upon notice from the code official, work on any plumbing system that is being done contrary to the provisions of this code or in a dangerous or unsafe manner shall immediately cease. Such notice shall be in writing and shall be given to the owner of the property, or to the owner's agent, or to the person doing the work. The notice shall state the conditions under which work is authorized to resume. Where an emergency exists, the code official shall continue any work in or about the structure after having been served with a stop work order, except such work as that person is directed to perform to remove a violation or unsafe condition, shall be liable of a fine of not less than one hundred dollars ($100.00) or more than five hundred dollars ($500.00). _______________ hereby declared unsafe. Any use of plumbing regulated by this code constituting a hazard to safety, health or public welfare by reason of inadequate maintenance, dilapidation, obsolescence, fire hazard, disaster, damage or abandonment is hereby declared an unsafe use. Any such unsafe equipment is hereby declared to be a public nuisance and shall be abated by repair, rehabilitation, demolition or removal.

      109.1 — General. In order to hear and decide appeals of orders, decisions or determinations made by the plumbing official relative to the application and interpretation of this code, there shall be and is hereby created an appeals process. The Director of Technical Assistance or the staff of the ICC Opinion Policy will provide the opinion of the ICC in writing, by telephone, or by E-mail. The final authority of code interpretations is the responsibility of the code official.

      109.2 — Limitations on authority. The process for appeal shall be based on a claim that the true intent of this code or the rules legally adopted there under have been incorrectly interpreted, the provisions of this code do not fully apply, or an equally good or better form of construction is proposed.

(Ord. No. 1879-2008, § D, 3-20-08).